Yes — a whole hotel can get new shower pans without relocating a single drain, and on most properties that is how the renovation should be run. The drain outlet is fixed in the slab or the framed floor; moving it means opening floors, re-piping and re-inspecting in every room. The pans, by contrast, are replaceable units. The job succeeds or fails on one discipline: survey the existing drains before the order is placed, room type by room type, and match standard pan sizes and drain positions to what is actually in the building — not to what the original drawings say should be there.
Why does the drain decide everything?
Almost every other element of a bathroom refit is adjustable on site. Tile can be cut, boards can be shimmed, finishes can absorb a few millimetres either way. A one-piece moulded pan cannot: its drain hole is where the mould puts it, and that hole has to land over the existing outlet closely enough for the waste fitting to connect and seal. If it does not, the pan cannot seat flat, the mortar bed cannot support it evenly, and the installer is stuck choosing between moving the drain — the expensive outcome everyone wanted to avoid — or sending the pan back.
So the sequence has to be reversed from the way purchasing usually works. The existing drain positions are the fixed specification; the pan selection is the variable. The good news is that hotels repeat themselves. A property may have several hundred bathrooms but only a handful of footprints, each repeated floor after floor. A finite, careful survey of those footprints covers the whole building, and turns “we hope the pans fit” into a known schedule of sizes and drain positions before the first pallet ships. The specification side is covered in our guide to SMC shower pans for hotel projects; this article covers the survey and the rollout.
What should the pre-order drain survey record?
Measure the building, not the drawings. Over decades of repairs, rooms get re-piped, pans get swapped for whatever was on the truck, and two rooms that look identical can have outlets in different places. The survey needs one complete record per room type, plus spot-checks of further rooms of the same type. Our drain position guide covers how to check a drain position from the studwork and finished wall; the checklist below is what to write down.
| Record for each room type | How to note it | Why it matters |
|---|---|---|
| Room type and room count | King, twin, accessible, suite — with the number of rooms of each | Sets the quantity needed for each pan specification |
| Existing pan size | Length × width of the pan being replaced | The starting point for matching a standard size |
| Drain centre from the short wall | Millimetres from the wall to the centre of the outlet | The dimension that decides whether the drain stays put |
| Drain centre from the long wall | Millimetres from the wall to the centre of the outlet | Confirms the position in the second axis — one axis is not enough |
| Drain outlet diameter | Measured at the outlet, e.g. 90 mm | Must suit the replacement pan’s outlet and the waste fitting |
| Threshold height | Height of the existing pan edge above the finished floor | Keeps the new low-profile pan consistent with the floor finish and door swing |
Two habits make the survey trustworthy. First, photograph each measured outlet with the tape in frame — if a number is questioned months later, the photo settles it. Second, keep an exception list from day one: rooms where the outlet is damaged, visibly off-pattern, or buried under a previous repair. Exceptions on paper are a line item; exceptions discovered during installation are a room out of service.
How do standard sizes cover most rooms?
The survey results cluster. Most rooms fall into a small number of size-and-drain combinations, and a standard range is built to land on exactly those combinations. The Serie L range, for example, runs in widths of 700, 800 and 900 mm with lengths from 800 to 1800 mm, all 26 mm high — so the survey usually matches a room to a size that already exists. Take one common footprint: the L-12080 is a 1200 × 800 × 26 mm pan with its drain outlet centre 200 mm from the short edge, a 90 mm outlet and a 126 mm square drain cover. If the survey shows a room type at 1200 × 800 with the outlet centre 200 mm off the short wall, that room type is a standard line on the order, drain untouched.
One caution: manufacturer drawings are schematic, and the revision in a brochure may not be the revision in production. Confirm the current drawing for each model against your survey figures before the order is finalised — a ten-minute check that protects the entire premise of the renovation. The pans help the rollout in two ways: the fall is moulded in at the standard slope of 1/4 inch per foot (2%), so no screeding judgement is needed room by room, and the anti-slip surface is rated Class C (DIN 51097). They are also light enough to move through an operating property — a 36 × 36 inch pan weighs 13.6 kg (30 lb), a one-person carry from service lift to bathroom.
How many spares per floor?
Spares are not pessimism; they are what keep a damaged or mis-surveyed unit from idling a crew. A common planning figure is one spare pan for each room type on each floor under renovation, plus a small attic stock held back for future single-room repairs — a later failure replaced from attic stock matches the installed batch exactly. Order the spares with the floor’s working quantity: pans travel 12 to a pallet, so a floor’s pans and its spares stack into the same delivery. Then inspect every pallet on arrival, before signing — corners, feet and drain covers, as set out in the shipping damage prevention guide. A spare you have inspected is a spare you can rely on at 7 a.m. on install day.
How does phasing work while the hotel stays open?
Most properties phase floor by floor; where the plumbing stacks allow it, phasing by vertical stack is even cleaner, because the wet trades stay within one riser line and the rooms above and below a work area are already out of service.
Either way, the per-room sequence is short because the drain stays where it is: strip the old pan, inspect the subfloor and the outlet against the survey record, lay the mortar bed, set the pan with full support across its whole underside, connect the waste, test, and close up. The plumbing scope in each room is a connection, not a relocation — that is the entire economic argument for the survey-first approach.Deliveries should follow the phases rather than precede them. A full-property order is container-scale — around 950 pans of 36 × 36 inch fit a 40HQ — but no operating hotel wants that volume in its loading bay at once. Split the order by phase, stage each delivery near the service lift for the floors under renovation, and keep the exception rooms for last in each phase: by then the crew has the standard rooms down to a rhythm, and the odd rooms get full attention.
Frequently asked questions
What if a few rooms have drain positions no standard pan matches?
Keep them on the exception list and treat them individually — they become the only rooms where a drain is adjusted, or they are matched after the current drawing has been confirmed with the supplier. A handful of exceptions handled deliberately is normal in an older property. What you should not do is let a few odd rooms push the whole building into drain relocation; that converts the cheapest rooms on the project into the most expensive ones.
Do replacement pans still need a mortar bed?
Yes. A one-piece moulded SMC pan is bedded on mortar and needs support across its whole underside, with no voids under the drain area or the standing surface. The slope is moulded into the pan at 1/4 inch per foot (2%), so the bed’s job is support and levelling, not creating the fall — but a pan that flexes because the bed has gaps will not stay quiet or sealed for long.
How accurate does the drain survey need to be?
Measure to the centre of the outlet from both walls, and record the outlet diameter, for at least one room of every type — then spot-check further rooms of the same type before ordering. If two rooms of one type disagree, survey every room of that type. A mismatch found in the survey costs a tape measure; the same mismatch found at installation costs a room-night and a rescheduled crew.
SMC Shower Engineering Team · Last updated: November 2026